Project Description
Customer Challenge:
Preventing pile runs during installation of 116 monopiles at the Rampion Offshore Wind Farm Project off the south coast of England.
Cranemaster Solution:
Two Cranemaster® shock absorbers with SWL of 1000 metric tons and 700 metric tons.
The Results:
The two jack-up vessels MPI Discovery and Pacific Orca installed the foundations using a 1000 metric tons crane to lift each foundation upright before lowering and piling it into the seabed using an hydraulic hammer. The installation was completed on schedule.